Hilton Garden Inn

We were subcontracted by Callahan, Inc. for this design-assist project in Brookline, MA. They were working with Claremont and Cambridge Seven to build a Hilton Garden Inn on a .486-acre parcel on the corner of Route 9 and Brookline Ave. We were brought early onto the project to assist CambridgeSeven with the design phase and were instrumental in the engineering of cladding. The building is mostly glass facade consisting of a unitized window wall system with many curving walls, complex setbacks, and challenging tight angles. These posed many engineering challenges, which we approached with commitment to support the design while ensuring weather tight detailing and efficient installation process. The collaboration included our involvement in multiple plant visits and mockup tests. The installation was challenging due to the precision required of the building geometry, but we proceeded at a fast pace. The unusually shaped, triangular building was wedged tightly between property lines and was clad in glass walls with some architectural panel work in various areas. The considerable amount of architectural panel work had to be modified based on some interesting challenges with the fins and depth in the original design. Our extensive experience with the planned cladding systems helped in the completion of this successful project. Key points Fabricated and installed Included two curtain wall systems- one at 37,341 sq ft and another at 5,366 sq ft Required 4,075 ln ft slab cover Received an Excellence In Construction Award in the Exteriors category from the Associated Builders And Contractors, Massachusetts Chapter, Eagle Award Gallery Edit gallery Read Letter of Recognition

Sunovion, 84 Waterford Drive

The Sunovion project consisted of the construction of a 143,000 sq. ft. new office building, which included 22,000 sq. ft. of composite panels and 23,000 sq. ft. of curtain walls. We fabricated all curtain walls, storefronts, panels and entrances in their on-site shop. The four story building was designed by Clifford Hoffman Associates of Boston, MA. The major challenge of this project was the construction of the 182 ft. connector bridge linking this new building to the existing Sunovion building. The sloping bridge was very complicated because the field staff had to verify and template many of the panels on the bridge. The installation process was tricky as the panels had to be placed around the exposed steel structure that was the backbone of the bridge. With us handling all of the custom fabrications, timelines were easily managed and met. The process was efficient as we were able to deliver the panels to the site one to two weeks after receiving the field dimensions rather than six to ten if they were manufactured elsewhere. Every step of this project was finished with diligence leading to a successful completion. Key points Included 22,000 sq ft of composite panels and 23,000 sq ft of curtain walls Incorporated a 182 ft sloped connector bridge Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

Smith College, Campus Center

The Smith College Campus Center was a unique project managed by the Daniel O’Connell’s Sons Construction Co. We were specifically chosen by Daniel O’Connell’s Sons because of the company’s expertise in furnishing and installing the types of designed systems that were required for the job. We were responsible for furnishing and installing the uniquely specified energy-efficient aluminum and glass systems in a multi-storied building requiring 18,500 sq. ft. of glass and frames. The design was created to maximize natural light throughout the building. The openings were picture framed with 2-3/4″ exposed accent trim at the top and bottom. This required us to apply the framing from the interior. It was an unusual but successful application. We also used a unique building design to interface vertical wall systems with the specially engineered continuous serpentine roof skylight that spanned the total length of the building. The goal was to create the look of continuous glass by tying into this skylight at the North and South ends. The main challenge for this project was the fast-track schedule that required us to close in the initial building within a six month turnaround period. The job demanded the overlapping involvement of several of our internal departments. After a team effort of the approvals process, the framing systems materials were ordered and the fabrication personnel were able to construct the specific frames needed. The field personnel were then able to progress with the installations. Key points Required 18,500 sq ft of energy-efficient glass and frames to maximize light Fast tracked schedule that we turned around in 6 months Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

The Art Complex Museum

The Art Complex Museum was built for the purpose of collecting, housing, protecting and displaying beautiful art for the enjoyment of the general public. In the fall of 1997, it was apparent that the old building was in need of new windows and entrances. We were hired to work in association with the architectural firm DiNisco Design Partnership to provide a practical and aesthetically appealing design for the new window systems. The window project entailed 3,000 sq. ft. of glass and it was 100% self-performed. There were several challenging aspects to this project. The main challenge being that the existing glass was insulated and field glazed into frames made on-site consisting of wood sills, steel mullions and a wood frieze board installed at the head over the glass. This form of glazing leads to glass failure and it is difficult to change a piece of glass without destroying it. There were 84 windows on this project and 68 of them had to be made in a curved slope. We created custom window templates which were then flown directly to the window manufacturer to match and complete the process. We were involved in this project from start to finish, and they personally made the measurements, engineered and installed the new windows. Key points Included 3,000 sq ft of self-performed glass 84 windows on this project and 68 of them had to be made in a curved slope Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

Tanglewood 2 Residence

This Tanglewood home is owned by architect Warren Schwartz and his wife, violinist Sheila Fiekowsky. Nestled in Stockbridge, MA, Schwartz designed this dream home to include a classically scored slender chevron, clad in glass and anodized aluminum, that followed the sloping grade for half of its length before going into a gravity defying 45 ft. cantilever. We were hired as a subcontractor for this and charged with fabricating and installing the curtain walls for the 45 ft. cantilever along with the main entry door, patio doors and windows throughout the home. This was a unique project as the production called for using commercial products for a residential application and providing a system that allowed movement in the cantilevered portion of the house after it was loaded and furnished. Visitors liken the sensation to a ride on a biplane or a magic carpet. “You feel like you’re in a high-rise building,” Schwartz says. The unique design and construction of this home became a feature story in multiple publications including the Boston Globe and the Wall Street Journal. Key points Fabricated and installed the curtain walls for the 45 ft. cantilever along with the main entry door, patio doors and windows throughout the home Featured in the Boston Globe and Wall Street Journal Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

UMASS Residence Halls

In January of 2006, the University of Massachusetts at Amherst was in need of new residence halls for their largely populated campus. We were hired as a subcontractor for exterior work on the new residence halls. The new residence halls were slated to be 195,840 sq. ft. We installed 1,002 aluminum projected windows and the aluminum composite panels. The main challenge of this project was its extremely aggressive schedule. The project needed to be done within a four month period. We met this deadline by temporarily merging with a glazing contractor to work on this project as a joint venture. They formed a great partnership and completed the job in a timely manner. Key points Installed 1,002 aluminum projected windows and the aluminum composite panels Completed in 4 months Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

Three Rivers Community College

We were the subcontractor for the renovation of 101,000 sq. ft. of existing space and the construction of another 190,000 sq. ft. building that was slated to replace all of the college’s labs. We were tasked with designing, fabricating and installing 28,591 sq. ft. of curtain wall and 6,412 sq. ft. of storefront. The challenge with this project was the preservation of the ongoing educational programs of the college and the adjacent Technical High School while constructing the new buildings and renovating the existing facility. R&R Window completed the project within one year. Key points Designed, fabricated and installed 28,591 sq. ft. of curtain wall and 6,412 sq. ft. of storefront Preservation of the ongoing educational programs of the college and the adjacent Technical High School while constructing the new buildings and renovating the existing facility Completed in 1 year Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

The Robert N. Giaimo Federal Building

The original 1970’s Robert N. Giaimo Federal Building was undergoing a massive renovation. Part of the renovation was to remove the small garage style windows that adorned the building and replace them with a stunning floor to ceiling curtain wall. We were hired as the subcontractor to manufacture and install the entire curtain wall and overall exterior façade. We installed 66,000 sq. ft. of curtain walls around East and West elevations and the South Entry. The challenge with this project was working on it in a busy pedestrian area. When we began work, the curtain walls needed to be installed from the top down when typically they are installed from the bottom up. Our solution included providing a newly designed curtain wall system that could be hung from the top down. Key points Removed small garage-style windows and replaced with ceiling curtain wall 66,000 sq ft of curtain walls Work took place in a busy pedestrian area with no injuries Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

UNH DeMeritt Hall

We worked as a subcontractor along with Harvey Construction Corporation on the renovation of DeMeritt Hall at the University of New Hampshire. We manufactured and installed 398 windows, the 2,200 sq. ft. curtain wall, 200 sq. ft. of storefront and flush panel aluminum doors. The challenge for this project was that custom designed caps were needed. We worked with an engineer from the manufacturer to design caps that would align and work with the curtain wall systems. These extra steps led to the successful completion of a unique job. Key points Manufactured and installed 398 windows, the 2,200 sq. ft. curtain wall, 200 sq. ft. of storefront and flush panel aluminum doors Created custom designed caps to align with the curtain wall systems Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us

WVIT-Channel 30

WVIT did a complete demolition and rebuild of their studio in 2008. We were hired to work in conjunction with the general contractor, Associated Construction Company, to build out this new 31,000 sq. ft. building. We designed, fabricated and installed two one-story curtain walls, 15 storefronts, and all glass interior partitions complete with glass doors and glass railing systems. The most pressing challenges were the continuous interior glass walls and doors and the interior glass rails. The field met this by verifying openings prior to the glass release. The complete construction of the building took just one year. Key points Designed, fabricated and installed two one-story curtain walls, 15 storefronts, and all glass interior partitions complete with glass doors and glass railing systems Included continuous interior glass walls and doors and the interior glass rails Completed in 1 year Gallery Edit gallery Read Certification Letter Let’s Get Started! Contact us for a project consultation. Contact Us